ha5roads

Steiner Ranch Pavement Preservation

Your Street Will Be Closing For Scheduled Maintenance

See The Map Below For Details On The Closures

WHY ARE MY ROADS CLOSING?

Holbrook Asphalt will be performing street maintenance in your area on behalf of the Steiner Ranch. The product being applied is a High Density Mineral Bond called HA5. The treatment will help significantly extend the life of the streets. The benefits of properly maintained streets include higher property values, a smoother/safer ride, and reduced costs to the community by prolonging the need for replacement.

Maintenance Schedule:

Asphalt Repairs and Crack Sealing: Nov 2025-Feb 2026

HA5 High Density Mineral Bond Installation: Spring 2026 – Dates TBD

**Click The Image To Enlarge**

PROJECT MAPS

This project is scheduled to take place beginning November 2025 with asphalt patching and repair, followed by crack repair. Weather permitting, these processes will continue through February 2026. The final phase follow in the Spring of 2026. Use the maps above to see which days work will be performed on your streets once those dates are finalized.

Work will commence from 7:00 AM to 7:00 PM. Streets will be closed during these hours and reopen in the evening.

NO STREET PARKING THE DAY OF WORK.

Cars left on the street during the work hours will be towed at the owner’s expense. Please also avoid parking within 50 feet of active work zones.

SHUTTLE SERVICE WILL BE PROVIDED:

A shuttle service is being provided for your convenience from 7am until 7pm while the streets are being treated. The shuttle will take you to/from your car. The shuttle service driver’s ability to recognize the curing stage of the newly installed surface treatment and the lighter weight vehicle makes this service possible. The contact number for the shuttle driver will be provided once project dates are approved.

WHAT IF I DRIVE ON THE ROAD WHILE CLOSED?

Driving on freshly treated pavement can damage both your vehicle and the new surface. Any repairs needed as a result will be the driver’s responsibility. Emergency vehicles will always be allowed through.

TURN OFF SPRINKLERS AND OUTDOOR WATER USE:

Pleases turn off your sprinklers and discontinue outdoor water use 24 hours before, during, and 24 hours after the closure. Water can ruin the treatment and could result in repair costs at the resident’s expense.

WEATHER CANCELLATION PROCEDURES:

If your street is canceled due to weather, THAT DAY will be rescheduled. All other days will proceed as scheduled. You will receive notification of your new closure date prior to the newly rescheduled date. You will not receive a cancellation notice (if we have removed the barricades, you can bring your cars back in), and you will not receive immediate notice of your new date. If you require earlier notification of your rescheduled closure date, please call the number, and we will be happy to let you know of any approved dates.

FREQUENTLY ASKED QUESTIONS:

Q: How will this affect emergency vehicles?

A: In the event of a life-threatening emergency, emergency vehicles will not be stopped from driving on the treated surface.

Q: How will we get our mail?

A: We have sent a copy of the maps to the local post office(s) to make them aware of the closures and requested that they make the necessary arrangements to ensure mail delivery. Please contact your local Post Office with any concerns about getting your mail.

Q: What should we do if we are expecting a delivery from UPS/FEDEX?:

A: Please reschedule any deliveries from UPS, AMAZON and FEDEX.

PROJECT CONTACTS:

HOLBROOK OFFICE @ 210-806-0920

Shane Pendergrass @ 435-773-7823